The Federal Government is seeking an additional $500 million loan from the World Bank to expand its renewable energy programme, a move that would push the bank’s total financing for the initiative to $1.25 billion amid persistent electricity shortages across Nigeria.
The proposed facility will augment the $750 million previously approved by the World Bank for the Nigeria Distributed Access through Renewable Energy Scale-up (DARES) project, currently being implemented by the Rural Electrification Agency (REA).
According to a World Bank Project Information Document (PID) prepared on November 13, 2026, and obtained on Sunday, the fresh $500 million request is scheduled for consideration by the bank’s Board of Executive Directors on December 18, 2026—three years after the initial loan was greenlit.
”This is a proposed Additional Financing in the amount of $500m for the Nigeria Distributed Access through Renewable Energy Scale-up Project. DARES was approved on December 14, 2023 and reached effectiveness on November 15, 2024,” the document stated. “The Project Development Objective is to increase access to electricity services for households, public institutions, and micro, small and medium enterprises with private sector-led distributed renewable energy generation.”
Endorsed by the World Bank’s Country Director for Nigeria, Taimur Samad, following an October 23 appraisal, the financing is designed to accelerate the deployment of standalone solar systems and mini-grids to underserved communities, schools, healthcare facilities, and businesses disconnected from the national grid.
Bridging Nigeria’s Massive Electrification Deficit
The borrowing request underscores Nigeria’s acute power deficit, which leaves households and enterprises reliant on costly petrol and diesel generators. World Bank data indicates that 87.2 million Nigerians lacked electricity access in 2024. Although the national electrification rate climbed from 52.5 per cent in 2015 to 61.2 per cent in 2024, rapid population growth has kept the absolute number of unserved citizens virtually stagnant.
The disparity is sharpest in rural areas, where only 32.9 per cent of residents have access to power. While the original DARES funding targets electricity connections for over 18.8 million people—roughly 22 per cent of the national access gap—the bank estimates Nigeria requires approximately $23 billion to achieve universal electricity access by 2030. Distributed renewable energy could connect more than 60 million people at a lower cost than conventional grid expansion.
Project Cost Surge and Co-Financing Breakdown
If approved, the new financing will adjust the International Development Association (IDA) credit component of DARES from $150 million to $650 million, alongside an unchanged $600 million in shorter-maturity IDA loans.
Consequently, the overall DARES project cost is projected to jump by 42.71 per cent (or $880.2 million), rising from $2.06 billion to $2.94 billion. Beyond the World Bank’s $500 million addition, the expansion incorporates $116.2 million from the French Development Agency (AFD) and $264 million in expected commercial capital—pushing total commercial financing under the programme from $1.028 billion to $1.292 billion.
Other co-financing commitments in the broader package include:
$193.8 million from the Japan International Cooperation Agency (JICA)
$49.1 million in trust fund resources via a United States Department of Justice-supported fund
$40 million from other development partners
Slow Disbursement Pace Raises Questions
Despite the push for fresh funds, World Bank transaction records up to October 22, 2026, reveal that only $128.44 million—or 17.13 per cent—of the original $750 million commitment has been disbursed. This leaves $621.56 million (82.87 per cent) yet to be drawn down, raising questions about the pace of financial implementation ahead of new borrowing.
However, the World Bank noted that fund releases are tied to strict regulatory reforms and institutional milestones, clarifying that $300 million has already been unlocked after the Federal Government satisfied two performance-based conditions.