The Federal Executive Council, FEC, has approved N87.538 billion for the construction of roads in the Federal Capital Territory, FCT, Abuja, Oyo, Kwara, Nasarawa, and Benue States.
This was disclosed at the end of the FEC meeting presided over by President Muhammadu Buahri at the Council Chamber, Presidential Villa, Abuja.
Minister of the FCT Mohammed Bello told newsmen at the end of the weekly council meeting that the contract for the roads in Abuja was awarded to Messrs Gilmor Engineering Nig. Ltd, at the sum of N30,686,609,298.68 with a completion period of 32 months.
The Minister said the council approved the award of contract for the full scope development of Umaru Musa Yar’Adua Way to the Northern Express Way (Murtala Mohammed Way) popularly known as Kubwa Expressway.
According to him, the project area is within Phase II of the Federal Capital City (FCC), serving as boundary road between the adjoining districts of Mabushi, Kado, Katampe and Jabi.
Bello said the project would improve access to the mentioned districts, improve security, as well as provide both skilled and unskilled employment to the people, adding that the road project would further enhance overall decongestion of traffic in phases I, II, III, IV of the Federal Capital City.
Also briefing, the Minister of Works and Housing, Babatunde Fashola, said his ministry presented two memoranda to showcase the commitment of the administration to complete ongoing and existing projects.
He said council approved a variation of N47.504 billion for the completion of the 52 kilometers-Oyo-Ogbomosho highway which is a part of the Ilorin-Ibadan 145 kilometers highway and that the variation had increased the total contract to N105.041 billion.
According to him, “We needed to adjust some things in the scope of work, the thickness of the pavement from 500mm to 560mm to also change the asphalt to polymer-modified bitumen and also the shoulders from surface dressing to fully asphalt inside and outside shoulder. So, all these required changes in prices of N47.504 billion
“This was the revision that we presented which council approved. This road was awarded in 2010. As I said, sections 1 and 3 were completed. We are trying to complete section 2 which we also inherited.”
He further said that council approved a N9.348 billion variation to complete Lokko-Oweto Bridge that links Nasarawa to Benue State, adding that the development has changed contract price from N51.621 billion to N60.961 billion.
He said: “The second similar project high we are trying complete is the Lokko-Oweto Bridge. That is the bridge across the River Benue that links Nasarawa and Benue states and provides a major time saving detour, about four hours, for people trying to come from south south, Benue, through to Nasarawa to Abuja.
That project was awarded in 2011 and it was awarded in three different sections – one section, the road to Benue…to Oweto, was awarded to one contractor, we have completed that road. The bridge was awarded to another contractor; the bridge is essentially finished now. It’s open to traffic. And then, Lokko to Nasarawa, 74 kilometers was awarded to another contractor. We are trying to sort out that problem and we will come back to it.
“So, the approval given today was a N9.348 billion variation to complete the bridge component or remaining work on the bridge. If you go there now, it’s already opened to traffic, finishing and …work to link the existing road in the Benue side to the bridge is what we got this variation for.
So, changes in contract price from N51.621 billion to N60.961 billion. As I said, even though we haven’t finished the road side on the Nasarawa side, the commuters are already using the road because it provides a huge detour going through Lafia, Keffi to come to Nasarawa and to Abuja.”